GM's Solar Supplier Is Pulling Back to Michigan Projects

GM's Solar Supplier Is Pulling Back to Michigan Projects CMS Energy is exiting renewables development outside its utility. The Branch and Lake Iris farms, now tied to GM through a virtual power purchase agreement, remain in the portfolio it is keeping. General

Illustrative imageIllustrative image

GM's Solar Supplier Is Pulling Back to Michigan Projects

CMS Energy is exiting renewables development outside its utility. The Branch and Lake Iris farms, now tied to GM through a virtual power purchase agreement, remain in the portfolio it is keeping.

General Motors (GM) calls it the largest clean-energy project in its history. In July, CMS Energy's board decided to sell more than 630 MW of NorthStar Clean Energy projects, most of them outside Michigan, and to stop developing renewables beyond its regulated utility, the company disclosed in its third-quarter filing. GM announced that it is the main customer for two NorthStar solar farms in Michigan under a virtual power purchase agreement (VPPA).

GM's Farms Stay With NorthStar

Neither farm is for sale. Branch Solar, a 200 MW project in Branch County, began commercial operation in June, and the 100 MW Lake Iris project in St. Clair County followed in August. Both belong to the roughly 1,442 MW of Michigan gas and solar generation NorthStar plans to hold, and each took on a tax equity partner this year.

CMS took a $456 million earnings hit in the third quarter from impairment, disposal and exit costs tied to the plan. A few sales have closed or are under contract, and the company is still in talks with buyers for the other projects.

The Contract Terms GM Kept Private

GM is pitching the deal as a way to steady a big expense. Chief sustainability officer Cassandra Garber wrote that long-term renewable supply makes a significant operating cost more predictable as AI and electrification change how companies think about power. Factories are already competing with data centers for megawatts. The automaker expects the farms to produce about 539,000 MWh a year, close to what Factory ZERO, Flint Assembly and Lansing Delta Township Assembly use together, and puts their combined investment near $550 million.

How much protection GM gets depends on numbers it has not released. In a virtual agreement, the farms sell their power into the wholesale market and the two sides settle up against a fixed price, while GM's plants keep buying electricity from their utilities. GM did not say what that price is or how long the contract runs, the terms that decide how these deals pay off for a buyer. The renewable energy credits will count toward emissions from the electricity GM buys for manufacturing.

A Fight Over a Power Line

Branch hit its own grid trouble along the way. In October 2024, its lawyers told the Michigan Public Service Commission that a transmission line proposed by Michigan Electric Transmission Company would run straight through the project, which they called three years and hundreds of millions of dollars in the making. They asked to join the case and argue for a different route. Delays of that kind have left some corporate buyers short of the power they contracted for.

Bethel Township, home to Branch, used the project to win a $1 million Renewables Ready Communities Award, money now going toward a township hall expansion and road work. GM says the two farms employed more than 550 construction workers.